Northern Expressway-Central Expressway In 2001, Euro Infra of Sweden under a grant from the Swedish International Development Cooperation Agency (SIDA) undertook a feasibility study for a 60km four-lane expressway between Kadawatha and Ambepussa costing Rs 19 billion or US$ 4 million per km. The EIRR (Economic Internal Rate of Return) was calculated at over 20% [...]

Sunday Times 2

Expressways: The journey so far

View(s):

Northern Expressway-Central Expressway
In 2001, Euro Infra of Sweden under a grant from the Swedish International Development Cooperation Agency (SIDA) undertook a feasibility study for a 60km four-lane expressway between Kadawatha and Ambepussa costing Rs 19 billion or US$ 4 million per km. The EIRR (Economic Internal Rate of Return) was calculated at over 20% p.a. without tolls and 16% with tolls. A two-lane road was recommended for the section from Ambepussa to Hadeniya costing a further Rs 9 billion or around US$ 2 million per km.
However, after the reopening of access to the North in 2009, the author, at the invitation of the RDA, proposed a trace for the Northern Expressway since it was evident that the North and the East were likely to attract much higher traffic levels than Kandy. The feasibility study which examined the potential road trace northwards from Meerigama found that a 41km section could be constructed at a cost of Rs 35 billion or at US$ 5 million per km for which the EIRR was a marginal 10% (for achieving traffic levels of around 17,000 vehicles per day by the year 2031).

However, in 2011, the Government procured the services of the Australian-based SMEC International consulting firm without tender to undertake just the feasibility study of a 198km Northern Expressway. Astoundingly, this contract cost over Rs 1 billion!

The initiative was intended to be a mammoth construction project of four sections costing Rs 600 billion. However, the SMEC feasibility study dated October 2013 makes some imaginative assumptions to justify this highway at 12.1% IERR. The RDA has played a Jekyll-and-Hyde role: It accepted the study by making nearly the full payment while also rejecting it on grounds of technical inadequacy. Notwithstanding this contradiction, the RDA went ahead and inaugurated construction in 2014.

Thus, SMEC had severely compromised its position. A subsequent review by a local university is also yet to be accepted. In any case, it has assumed the same RDA-estimated cost for the project without any verification or comparison and, thus, cannot be considered as a full and independent study.

While the entire country expected the new government to reexamine these highway projects, the opposite is true. There were superficial changes–such as shifting the starting point from Enderamulla back to Kadawatha, changing the name of the project from Northern Expressway to Central Expressway, and altering the starting point of the extension to Kandy. But the same project is proceeding as before.

In December 2015, Cabinet decided to obtain technological and financial proposals from the Metallurgical Corporation of China for the section from Kadawatha to Kossinna–a stretch that was to have been built with savings from OCH3. It was revealed a few weeks ago, however, that the entire Section 1 of 36.5 km is to be awarded to this same company for Rs 158 billion. This works out to US$ 30 million a km, 10% more than the cost per km before the elections!

The China Exim Bank with whom the Government has entered into an MOU has recently asked for a feasibility study for Section 1. The RDA has supplied a cut-and-paste job using material from different studies, including reports it had previously rejected. This is the sad plight of a country about to embark on its biggest investment in history, much larger than the Mahaweli project.

Based on previous feasibility studies, which were done in an acceptable and transparent manner, the negotiated cost appears inflated several times. At this price, the traffic-heavy Section 1 will not yield a return rate of more than 4-5% p.a., indicating that it will be an extremely poor investment.

Last week, the Government announced that Section 2 has also been awarded–this time to consortia of local contractors for Rs 137 billion at US$ 24 million per km. As before, there is still no accepted feasibility study for this section at this expenditure. With traffic levels, that would only be a fraction of Section 1 and time savings that are even less, it is likely that at this higher negotiated cost, it would end up with negative economic returns.

It is widely known that expressions of interest were called from local construction companies for Section 2. But instead of calling competitive bids, the RDA formed consortia to negotiate costs for design-and-build so that there was only a single bid for each subsection.

For Section 3, limited bids are being called from Japanese companies. The media reported that the same Japanese company which provided the opportunity for the first large-scale cost escalation for the OCH2 during the previous regime is now in the picture again. Speculation is rife that Section 4 has also been awarded by negotiation to Chinese contractors. Hence it appears to be open-season yet again for highway robbery.

Southern Expressway
A 1997 feasibility study for the Southern Expressway led by this author estimated the cost of the four-lane 131km highway from Kottawa to Godagama in Matara at Rs 20.4 billion (US$400 million) at a cost of US$ 3.1 million a km with an Economic Internal Rate of Return (EIRR) of between 19% and 25%. This indicated that it was a favourable investment.

In 2000, the Japan International Cooperation Agency (JICA) and the Asian Development Bank (ADB) financed this project after International Competitive Bidding (ICB). In 2006 some of the contracts were re-negotiated due to political initiatives that led to converting two lane sections to four lanes. With this the final cost at completion was an increase of over 200% to US$ 10 million per km. An economic analysis using the higher cost and lower benefits represented by lower-than-estimated traffic volumes reduces the actual rate of return to 10-12%, making this barely justifiable.

The next phase of the Expressway, the 30km section between Galle and Matara, was awarded on a negotiated basis to a Chinese contractor in 2011 with financing from Exim Bank of China for a contract value of Rs 18.7 billion (US$ 165). This was not on competitive bidding. But since proper estimates and designs were available, the final cost was a modest US$ 4.5 million per km– the only such contract to be favourable.

The final section of the Extension of the Southern Expressway from Matara to Hambantota, a 74 km section also studied by this author in 2007, was found to be feasible provided that proposed development in Hambantota preceded the construction of the highway. The cost was estimated at Rs 33.2 billion (US$ 300 million) or US$ 4 million per km. The EIRR was estimated to be only 6.2% p.a. with a recommendation was for delayed construction.

However, in 2013/14 the Road Development Authority (RDA) awarded this highway on negotiated design-and-build basis to Chinese companies for a total contract value of Rs 224 billion (US$ 1892 million) amounting to US$ 20 million per km. Given that the anticipated primary industries in Hambantota have not materialized and that the cost has escalated from US$ 4 to 20 million per km, the economic return from this 96km project will be negative and a significant loss.

Colombo-Katunayake Expressway (CKE)
In 2008, a design-and-build contract was signed with a Chinese firm for a cost of Rs 32 billion (US$ 320 million) for the 26km four-lane highway. While there is no comprehensive economic feasibility study available, an internal RDA report dated 2008 stated that traffic levels on the CKE would reach over 50,000 vehicles per day by 2016 and that the rate of return would be 14.1% p.a.

The current traffic levels, however, are less than 50% of estimated. With the final cost of the highway at US$ 353 million, the actual EIRR translates to a marginal benefit of 10%p.a.

Outer Circular Highway (OCH)
The study for this was completed by Oriental Consultants of Japan in 1999. It was found to be economically feasible with a rate of return of 18.9% p.a. for a four-lane highway to be constructed in four sections. The cost of two sections was to be financed by the Japan Bank for International Cooperation (JBIC). In 2009, the first section (OCH1) of 11km between Kottawa and Kaduwela was awarded on ICB to a Chinese firm. Its cost was US$ 212 million at US$ 19 million per km.

In 2012, the Japanese restricted the second section (OCH2) between Kaduwela and Kadawatha to Japanese contractors resulting in one company submitting a proposal at a very high price. Even with a recommendation to re-bid, the Government in 2012 decided to award it to the same company following superficial negotiations. The cost for this 9km section was US$ 329 million (at US$ 43 million per km), a significant increase over OCH1.

The initial feasibility study made by Oriental Consultants–a leading Japanese engineering consulting firm with extensive international experience–estimated the cost at just US$ 120 million for OCH1 and only US$ 80 million for OCH2. The actual cost of construction was 100% more for OCH1 and a phenomenal 300% more for OCH2.
The traffic level of the OCH in 2016 is less than 50% of what was estimated, indicating that the rate of return of the OCH1 would drop significantly and in OCH2 even turn negative.

The third stage of the OCH from Kadawatha to Kerawelapitiya was also awarded in 2013 on a negotiated design-and-build basis with financing from China Exim Bank. The contract value for this 9km highway was negotiated for Rs 66.7 billion (US$ 535million), amounting to a record US$ 59 million per km. The actual cost estimated by Oriental Consultants of Japan for this entire 9km section was only US$ 50 million.

The RDA has not carried out a feasibility study for the revised cost. Sadly, the Exim Bank which provided this loan does not seem to follow the practice of other international lending agencies in asking for a rigorous study. This was pointed out by the writer prior to the Presidential elections. The current Government, a few months afterwards, announced a negotiated reduction in the cost. This circus act however, enabled the OCH3 contractor to negotiate and secure the first stage of the Central Expressway without competition as the so-called saving (which has now transpired to be almost nil) was transferred to that construction to avoid calling for international bids. This means this section too will have negative returns.

Advertising Rates

Please contact the advertising office on 011 - 2479521 for the advertising rates.